Understanding Labor Rate Variance
Labor rate variance (LRV) is a measure of the difference between the actual labor costs incurred and the standard labor costs that were budgeted for a specific production activity. It helps businesses understand how efficiently they are managing their labor costs in terms of hourly wages.
Why is Labor Rate Variance Important?
- Cost Control: LRV highlights deviations from planned labor expenses, allowing management to investigate and address cost overruns or savings.
- Performance Evaluation: It can be used to assess the performance of supervisors or managers responsible for labor scheduling and cost management.
- Budgeting Accuracy: Understanding historical LRV can improve the accuracy of future labor cost budgeting.
- Pricing Decisions: Accurate labor cost calculations, informed by variance analysis, are crucial for setting competitive and profitable product prices.
How to Calculate Labor Rate Variance
The formula for Labor Rate Variance is straightforward:
Labor Rate Variance = (Actual Labor Rate per Hour – Standard Labor Rate per Hour) x Total Hours Worked
In this calculation:
- Actual Labor Rate per Hour: This is the average hourly wage actually paid to workers during the period.
- Standard Labor Rate per Hour: This is the expected or budgeted hourly wage for the labor involved.
- Total Hours Worked: This is the total number of hours for which labor costs were incurred.
Interpreting the Variance
- A positive variance (favorable) means that the actual labor rate was lower than the standard rate, resulting in cost savings. This could be due to using more junior staff, lower overtime rates, or negotiating better wage agreements.
- A negative variance (unfavorable) means that the actual labor rate was higher than the standard rate, indicating an increase in labor costs. This might occur due to using more senior (and thus higher-paid) staff than planned, unexpected overtime at higher rates, or increases in wage rates.
Example Calculation:
Let's consider a scenario:
- Standard Labor Rate per Hour: $25.00
- Actual Labor Rate per Hour: $28.50
- Total Hours Worked: 100 hours
Using the formula:
Labor Rate Variance = ($28.50 – $25.00) x 100 hours
Labor Rate Variance = $3.50 x 100 hours
Labor Rate Variance = $350
In this example, the variance is unfavorable because the actual labor rate was higher than the standard rate, leading to an additional cost of $350.